Find out answers to the 5 questions given at the end of table below: - The working is to be based on the information in the following table Activity Duration Predecessor a 4 None b 6 a c 4 a d 2 c e 4 b f 5 b, d g 3 c h 4 f, g i 2 e, h Please carry out the following exercise-- Construct the network diagram. Find each activity's Earliest Start, Earliest Finish, Latest Start, Latest Finish and slack. Identify all paths. Which path is the critical path? Calculate the slack for each activity. How long will it take to complete the project